Fairfax County Public Schools

Project Background

Reynolds Consulting Engineers (RCE) was hired by the Fairfax County Public Schools to provide commissioning services in an open-ended contract. As part of the Fairfax County Public Schools program, RCE was assigned to provide commissioning services for the following projects:

Project Specs

Laurel Hill Elementary School
98,000 square feet
Completed in 2009
Construction cost: $20 million

Lutie Lewis Coates Elementary School
95,000 square feet
Completed in 2009
Construction cost: $19 million

Edison High School
50,000-square-foot addition and renovations
Completed in 2012
Construction cost: $65 million

Westlawn Elementary School
23,000-square-foot addition
Completed in 2011
Construction cost: $21 million

Lacey Center Elementary School
36 classroom addition
New geothermal heating project
Completed in 2012
Construction cost: $25.5 million

Franconia Elementary School
Renovations to library, art room, stage, and technology
Completed in 2012
Construction cost: $20.6 million