Conemaugh Valley School District

Project Background

The Conemaugh Valley School District awarded Reynolds a contract to provide an investment grade energy audit and a performance contract to improve the energy efficiency at Conemaugh Valley High School.

The tightly focused scope of work included lighting improvements throughout the building, replacing old and inefficient burners and controls on the two boilers, installing new high-efficiency motors and variable frequency drives on the hot water pumps, and water conservation measures.

Since completing the performance contract, Reynolds has been rehired by the district to provide a retro-commissioning study of the heating distribution system of the Conemaugh Valley High School.

Project Specs

Solution: Energy
Project Cost: $367,754
Guaranteed Annual Savings: $25,784
Year 1 Savings Measured: $33,236