Project Background

The Abington Heights School District awarded Reynolds a contract to provide an investment grade energy audit and a performance contract.

The guaranteed energy savings project included work at the Newton-Ransom Elementary School, the Abington Heights Middle School, and the Abington Heights High School.

The $4.4 million contract included converting the boilers at the elementary school to dual fuel capable ones, converting the HVAC system at the middle school from electric to natural gas and installing an updated building automation system, installing a new roof on the middle school, and installing a split system A/C in the district’s computer system server room.

Project Specs

Solution: Energy
Project Cost: $4,467,636
Guaranteed Annual Savings: $97,325
Year 1 Savings Measured: $119,231